in this video you are going to learn
what a project scope statement is and
how to use it in project management also
I will show you an example hello and me
to the film project management basics
and I help people just like you to
become a project manager if you want to
become a PM you are in the right place
subscribe to this channel right now
before we talk about project scope stay
tuned
let's review its place in project
management framework
we do need some inputs before you can
start drafting it out it all starts with
a project charter this document contains
high-level information about the project
and its boundary it might be as simple
as a web application for our corporate
clients or one-story house with a garage
then we'll find the relevant project
stakeholders who have expertise and
authority to provide specific
requirements first your clients provide
the main requirements then you collect
relevant requirements from your team and
subject matter experts within your
organization together you work to find
detailed requirements if needed to
create a requirements traceability metal
okay just to be sure we're on the same
side let's clarify the difference
between the scope of work and the
requirements a requirement is a
condition or capability that is required
to be present in a product service or
result to satisfy a contractor formally
import specifications and a project
scope is the work performed to deliver a
product service or result with the
specified features and functionality
described in a contract or are the
formal impulse specification so what
does it mean a requirement is what a
product should look like what should it
be capable of what are the
characteristics behavior performance and
so on while project scope describes what
work should be performed to meet all
those requirements so only once you know
the main requirements you can outline
the project scope that's where you start
drafting the project scope statement
project scope statement is
the description of a product and project
scope it is used as a written
confirmation of what your project is
going to produce and how what's the key
to useful projects scope statement I
believe you need to use terms and
language that any stakeholder
understands these piece of projects cool
Breslin is mainly for your customers and
clients what should be included
justification of a project project scope
acceptance criteria deliverables
projects exclusions constraints and
assumptions okay if you watched until
this moment leave me eight years in the
comments below because now we are going
into the main part of this video I will
explain how to create a project scope
statement on an example of a simple
project let's imagine I work in a web
development studio and I need to create
a project management basic site as it
looks now let's do it justification of
the project it is a short description of
business need sometimes one sentence is
enough the rest should stay in the
project chart in our case as a project
management blogger I need a platform to
host my articles on project management
and build audience of loyal readers it
is a cornerstone of my business product
scope here you put description of all
the characteristics traits and
functionality of a product or service
that you need to produce keep in mind
that you collected requirements from
different stakeholders do not assume
that all of them communicate with each
other so it is the primary place to
align the expectations of all key
stakeholders you need to show the amount
and complexity of work required to meet
different requirements put the most of
your efforts in this section in our
example we need to deliver a website
based on WordPress it's the platform
that have all the internet uses with
minimum custom software development the
site means the home page blogger curve
and article template as it was designed
and a special forum to collect emails
again keep in mind that by this moment
we need to have memory
already specified acceptance criteria
these are the conditions that must be
met before the project deliverables are
accepted you can include an acceptable
level and the number of defects here as
well we agreed that this is delivered
when I can access PM basics one on one
dot-com site on the internet and seal
the main deliverables
there should be no defects that prevent
using the main functionality or doesn't
have a simple workaround visually and
functionally the site should look and
perform as described in specifications
and designs currently provide a sign off
on the final results we are not writing
a contract here it's an agreement it
should be readable and easy to
understand don't try to cover your back
here you can do it by providing a
realistic project management plan late
deliverables it is the description of
all deliverables your project will
produce it may include the project or
service project documentation product
menus educational materials for your
product and so on so put all tangible
and intangible results that you need to
hand off to the client at the end of
your project so in our example the
client wants to get some project
management deliverables like water
breakdown structure and project schedule
and product deliverables first home page
with text images and form to collect
emails second blog archive at least 10
recent articles with sidebar thought
blog post template so that all articles
have the same feel in book all I need to
do is to fill it with content text and
images for example I also want to have
this little form at the end of each
article project exclusions here you need
to specify what is out of the project
scope quite often a part of stakeholders
want something specific the other part
of stakeholders or customers does not
support it so it's a config situation
but once the conflict is resolved and it
was decided to remove this part of scope
from the pro
you put it here in the project
exclusions it says time in the future
firstly you will not have to revisit
this project exclusions again but
stakeholders may try to include them
later during the project execution
however unless something dramatically
changes you should not waste time on the
reviewing exclusion secondly unless it's
clearly stated someone may still expect
you will deliver this part of scope
don't feed false expectations it will be
easier to handle the project at the end
in our example website will be created
on WordPress so custom software
development is beyond this project
students only area for the perfect
junior project manager program is out of
the scope of current project we need
these exclusions to ensure that even if
we have time and money we don't drift
away from reaching our main objective to
deliver website with the blog
constraints anything that limits you to
deliver the product efficiently should
be stated here so from project charter
we have project budget constraint which
is $1500 there is a deadline on August
25 in the way constrained by technology
options we can only use WordPress please
notice that this constraint might not be
mentioned in the project charter early
at the project beginning assumptions
these are the uncertainties that
couldn't be clarified at this moment you
may need to accept some of them during
planning in case an assumption proves to
be invalid you have a right to modify
the project plan so in our case our
assumption is that it's possible to
deliver a project using standard
WordPress capabilities also we should
assume that this form will integrate
with WordPress seamlessly okay here is
an important aspect a customer a client
should approve the project scope
statement in fact it's a 4:1 and mutual
agreement it states that you are
committed to delivering described
results and
they identified assumptions and with
being clear constraints on the other
hand customers agreed to accept these
specify the results but what's more
important you will continue planning
project based on the information
approved in the project's cost statement
you will break down major deliverables
to identify 100% of scope
it means you estimate cost and duration
only all the tasks required to produce
these deliverables it doesn't mean that
we cannot change the project scope no it
means that to mallika change we need to
amend the agreement however well there
is a change request from customers
during project execution and it's not
described in the initial project scope
statement it's a valid reason for you to
make adjustment to project budget
schedule and other parts of project
management plan that's why it's so
important to read project scope
statement using tools and language that
your clients understand it's a mutually
beneficial document that prevents
conflicts in the future how do you use
project scope statement without ideally
you simply take the main deliverables
and put them on the first level of
decomposition into the work breakdown
structure then you decompose them
further until you get to the level
suitable for estimation also you can use
assumptions and constraints from here as
initial input to their risk management
activities okay if you liked this video
and it's time for you to become a
project manager subscribe to this
channel also do check additional
resources in the description below but
before we go let me ask you a question
what do you think is the biggest benefit
of the projects called statement is it
understanding all the projects scope by
customer or your ability to refer to the
scope statement when a change request
comes leave me a comment below thank you
in advance